When importing a new project to Dash360, a specific import order needs to be followed. If you have imported a new system to Dash360, the import order is almost exactly the same. The order is as follows:
  1. WBS Codes
  2. Rates Files
  3. Resource Files
  4. Resource Results
  5. Resource Calculations
  6. Work Package Codes
  7. Assign Codes to Project (Not an import)
  8. Cost Estimates
  9. Resource Assignments
This is the base requirement of data needed to create a functioning project in Dash360.