- Cost Estimate Form: A view icon (magnifying glass) now appears if you can only view a Resource Assignment. This occurs when you don’t have edit access, when the Project is locked, when the Work Package is read only or if it is an Earned Resource Assignment.
- Cost Estimate Form: The process icon for Move / Copy Resource Assignments is now not possible from the UI for Earned or Actual Resource Assignments. You can also not Move Budget Resource Assignments that have Earned Value attached to them. This is to insure that Dash360 and your project’s EV does not get messed up.
- Cost Estimate Form: You can no longer delete a Budget Resource Assignment if it has Earned Value attached to it. You also may not delete Earned Resource Assignments from the UI. You also cannot Edit Earned Resource Assignments from the UI.
- Cost Estimate Form → Import Timephased Data: You can no longer import Earned Resource Assignments in using the Timephase import. Use the Admin → Import → Resource Assignment Import instead. CAMs also cannot import Actual Resource Assignments using this import.
- Cost Estimate Form → Edit Resource Assignment: If your project has the Do Not Change Historical flag turned on, you used to be able to modify values in the past from the UI. This is now corrected so you cannot do that anymore (as expected). Also, sometimes the datagrid would collapse and every cell in the grid would be super small. This has also been corrected.
- Cost Estimate Form: If you copy a work package, the Earned Resource Assignments for that work package are not copied with it. All other resource assignments, however, are copied.
- Cost Estimate Form: Removed the print button from this page as it did not work. New download options will be coming in a future release.
- Cost Estimate Form → Schedule: If you showed Earned Resource Assignments on the form, the Edit and Delete icons for the Schedule area would disappear. This has been fixed.
- Cost Summary Report: The Show / Hide Work Packages feature didn’t always reflect correctly on the screen. This has been corrected.
- Variance Narrative Report: Fixed the Send to Admin button so it now works. Also updated the text to be more readable.
- Fixed behavior around the contraint date. Also fixed some issues with the Duration field. All added original duration to activities and added a contraint data type to activities, too. The Duration is also calculate based on start/end date changes on the activities modal.
- The Work Package and Work Package Number fields in the Dashboard returned the same values. Now, the Work Package Number returns just the number. The Work Package field returns the number and it’s description.
- Custom code fields and custom notebook fields pulled all values when there were multiple custom notebook fields or custom code fields.
- Recalculate Project: When you recalculate a project the system now will recalculate all Resource Assignments except the Earned Cost Class. This is unless you have the Do Not Change Historical Data flag turned on. If that is set and your reporting period for the project is set, then the system will not allow you to change any data prior to the reporting period.
- Export Resource Assignments: Made enhancements to the RA Export to make it faster. Also fixed the Resource Code filter so it shows the Resource Code and the Description. Before it was only showing the description.
- Import Resource Assignments: If you imported resource assignments with a finish date before your start date, the system would just skip the record. Now, it throws an error message asking you to fix the issue.
- Backup / Restore Projects: When backing up and restoring projects, the Format 1030 Code file was not attached to the new restored project. This has been corrected.
- Edit Code: When editing a code, it would not let you change the code name even if nothing was attached to that code. This has been fixed.
- New Project: Creating a new project after editing an existing project and then selecting a tab would cause an error. This has been corrected.