- Cost Estimate Form: If you opened a read-only / Earned Resource Assignment to view it and then closed the Edit Resource Assignment modal, all of the buttons and text fields on the underlying Cost Estimate Form would be disabled. This has been corrected.
- Cost Estimate Detail Report: Modified the PDF export all option to show dates formatted without time. Also, this export now adheres to the date format set in the registry.
- Tableau: We added the Form 1030 codes and description to the Tableau Dashboards.
- Form 1030: Added a Resource Assignment version of the report with RA notebook fields as columns.
- Copy Project: If you had Resource Assignment Notebook fields and you copied a project, those entries were not moved to the new project. Instead, they were kept in the old project. This has been corrected.
- WBS Tree: The WBS Tree had numerous enhancement. You could not renumber the top node of the tree from 1 to 01 and vice versa. Now, you can do that. You can also modify all of the descriptions. There also was an issue were all child codes would not automatically get update when changing a parent. Also fixed an issue with importing and changing child codes when editing a parent code in the Admin → Codes → Edit Code area. There also were issues where the Edit and Delete icons would not show up on the last child node. All of these have been corrected.
- Codes Import: When importing WBS or Work Package codes, sometimes the system would not auto update all references to the WBS and WP through out the system. There was also an error in the Cost Estimate import that was also causing issues when changing codes. This has all been corrected.
- Calculate Earned Value: The Calculate EV dialog now shows a year and month calendar widget instead of a full calendar widget that also includes days.
- Calculate Earned Value: % Complete and Milestone % Complete would calculate a 0 value for a reporting period if the main rate for a resource assignment’s resource code had not started yet. This has been corrected.
- Calculate Earned Value: The Earned as Spent EVT required that Actuals be entered in the correct resource type (labor, nonlabor or travel) to get Earned Value in the respective resource type. Now, EV doesn’t care what resource type the Actuals are in to create the Earned records.
- Recalculate Project: If a project needs to be recalculated, the process icon turns a light orange color. Now, the Recalculate Project submenu item under that process icon also is a light orange color.
- Import Form 1030 Results: When importing Form 1030 Results, there was a way to allow you to upload duplicate records. This has now been corrected so dupes are not allowed.
- Registry: There is now a registry field called Date-Prefix-Heading-For-Reports. This field can be used to change the default “FY” text in some reports to whatever prefix you’d like. In order to work, the Admin → Edit Project → Calendar property must be set to Fiscal.
- Tableau Dashboard Designer: Added the refresh dashboards button on this screen, too.
- Tableau Dashboard Designer: When deleting a dashboard, an error was thrown. This has been corrected.