- Earned Value → EV Curves: This report has been rewritten to make it faster and to also with some additional improvements. The EV Curve data now shows all Budget data to completion in 1 line graph for Budget (removed the Budget at Completion series). Also fixed the Graph Data tab so it correctly shows all data that is in the graph. A caching layer has also been added to make filtering faster.
- Admin → Users: If a CAM is changed to an Administrator, the system now alerts you to tell you that all existing CAM permissions that have been setup will be deleted from the system. Administrators have access to everything in Dash360, so setting a CAM to an Administrator will wipe out their existing privileges and give them access to every module, project, WBS and work package in the system.
- Schedule → Schedule Builder / Admin → Import Schedule: You can now import activities without selecting a Work Package. This field used to be required. Now, you can create an activity and just assign it to a WBS. This is useful for top-level activities that need to occur but are not necessarily assigned to a Work Package.
- Estimating → Work Package Report: If the WBS Dictionary is filled out, it will now show directly under the WBS instead of at the bottom of the Work Package Report.
- Tableau: The main menu now will show Report → Tableau Dashboards and Admin → Tableau Dashboard Editor depending on whether a Dash360 user has a Tableau license or not. If a user does not have a license, then these menu items will be hidden.
- Admin → Import Resource Assignments → Map Earned Records: Mapping Earned RAs to Budget RAs modal now has a download option that allows you to download the mappings to an Excel file so you can better manage how to map them.
- Estimating → Cost Estimating Form → Override Contingency: If you chose to override the contingency on a resource assignment or work package and entered a value <= 0, the system would not correctly update your contingency. This has now been corrected so a value <= 0 is seen as a valid contingency percentage.
- Estimating → Cost Estimate Form → Copy Work Package Link: This feature did not correctly copy the work package link. It sometimes was missing the Work Package Number. This kept the shortcut link from working. It has now been corrected so the shortcut link works.
- Estimating → Cost Estimate Form → RA WYSIWYG Notebooks Error: If you had a WYSIWYG Resource Assignment notebook field attached, then the system would not allow you to save the Details section of the Cost Estimate Form. It would throw a javascript error. Also, the Add / Edit Resource Assignment form would not show the RA WYSIWYG field correctly. Both of these issues have been corrected.
- Earned Value → Project Explorer: There were certain cases where the timephased dates on this page could get out of order. This would happen if you were viewing the Project Explorer using a user view and you were switching between project with different overall start and end dates. A fix has been implemented to keep this from happening in the future.
- Schedule → Schedule Builder → Add / Edit Activity: When creating a milestone, the system would automatically set the Duration of that activity to 1. However, all milestones should have a Duration of 0. The system has been updated so all new milestones will have a Duration of 0.
- Admin → Resources → Resource Calculations: When creating a resource calculation, the system used to allow you to use the same Resource Result (FTE, Hours, Direct, Escalation, etc) on multiple lines in the same resource calculation. Dash360 cannot support this kind of configuration. Every Resource Calculation row must have a unique Resource Result. The code has been updated to not allow an admin to perform this error in the UI.