- CAM Summary Report: Created a new Summary Report by CAM. This report allows you to select a Project and a CAM and see all WBS and WorkPackage costs and breakdowns rolled up by CAM.
- Cost Estimate Detail Report: The Total column was removed from the Labor, Non-Labor and Travel datagrids. In it’s place we added a “Results Total” column that dynamically adds up all visible, currency result-based columns (Direct, Escalation, Fringe, etc). This allows you to see a running total of just the results you care about and makes the report more useful. We also modified the Contingency column to dynamically recalculate itself based on just the results you have visible. In addition, we removed the Total + Contingency column and changed it to a dynamic “Results Total + Contingency” that works as described above. Next, the Activity Summary and Contingency Summary totals also update themselves to match the new dynamic totals based on the results you have shown. Finally, the download functions were updated to support all of these changes.
- Format 1030 Report: Two new columns were added to this report “FY Total” and “Results Total”. If the FY Total column is visible in your datagrid, then the report will now dynamically sum all other columns starting with “FY”. This allows you to hide / show FY columns and have the FY Total column show the correct value. The Results Total column works similarly except it adds up all visible, currency result-based columns (Direct, Escalation, Fringe, etc).
- Activities Resource Assignment Report: Updated this report so that the sum totals do not include non-currency values. The sums were incorrect because values like FTE, Days, etc were getting included in the totals.
- Tableau: Fixed the refresh button so that Tableau dashboards now will always properly refresh without error.
- Schedule: Added a Total column to the Resource Level pane at the bottom of the Schedule Builder / Viewer. This allows you to see the sum total of the units shown in the resource grid.
- Admin → Import Resource Assignments: When importing a large number of resource assignments with earned records in the import file, the import would error out trying to show the Earned Resource Assignment mapping screen. Dash360 has been modified to not error out in these scenarios.
- Changed the column header in the Cost Estimate Form Timephase Export from Snapshot Name to Project Name.
- Cost Estimate Form: When adding a decimal into the Risk Factors → Contingency Override field, the system would throw an error. This has been corrected.
- Fixed a bug where the Cost Estimate Form would fail if you had the same notebook field attached at both the work package and resource assignment level. Fixed this issue so Dash360 allows you to do this configuration.
- Added a way to toggle HTTPS redirection on/off per client instance. This is needed for some clients who have their own domain. SSL certificates often have to be renewed and verified using the HTTP address of a server. This allows SSL certificates to be renewed more easily going forward.