- Export to PDF, PNG or Excel: You can now export the Gantt chart and it’s tasks to PDF, PNG or Excel.
- A new feature has been added to the flyout filter that allows you to expand or collapse all grouped nodes in the Gantt chart.
- If the Work Package or CAM fields are empty, the system now says “No Work Package” or “No CAM” instead of “null”.
- The Tasks now show the minimum Start Date, the maximum Finish Date and the sum for the duration column for each group in the Gantt.
- You can now group the Schedule Builder and Viewer by WBS Levels.
- We have moved the Schedule Builder to the first menu item in the Schedule section. We also changed the “Schedule Viewer” to “Schedule View & Status”.
- If a project or the schedule on a project is locked, you will no longer be allowed to use the Schedule Builder. A message now appears telling you to use the Schedule View & Status page instead. This is to prevent changes from occurring to a locked project.
- Added a currency sign and commas to all resource values that are currency based resource results.
- In the Schedule area of the Cost Estimating Form, you now can see a total cost for the value of each task. If you click on the orange triangle recently added to the task, you now will see all resource assignments assigned to that task. You will also see the cost applied of each resource assignment to that task.
- Project Explorer: Added a Yearly option to the project explorer that shows all of the resource results for a resource assignment by year. You can not edit the data in the grid in the Project Explorer while in Yearly view. However, you can still edit the data in the Monthly view.
- Risk → Risk Register: Renumber a Risk ID. If you have previously created a Risk ID and need to renumber it, you can now do that from the UI. Just click on the new process icon next to a risk and choose Rename Risk ID option. Select your new Risk Prefix and enter a number and your existing Risk ID will be renumbered.
- Activities by Resource Assignment: Added a Totals column that sums all of the other columns in the report.
- Admin → Projects → Notebooks: Create a new Calendar Notebook field. Dash360 now allows you to create Calendar / Date notebook fields to add onto your Cost Estimate Form, Resource Assignments, WBS Dictionary or Risk Register. Just create the new Calendar notebook field and attach it to your project. Clicking on your new Calendar notebook field will show a popup calendar where you can easily select the date and save it.
- Export → Schedule by Resource Assignment: Added a description column to the export file.
- Admin → Import → Rates: If you are importing rates and you change a rateset name to a new value, Dash360 will now go through all of your resource calculations with that old rateset name and update it to the new rateset name. In order for this feature to work, you must update all rates with this old rateset name.
- Risk → Risk Register: On the Add/Edit a Risk form, the Impact → Probability % field would not allow you to enter a decimal in your percent. Entering 12.5% would result in the system storing 13%. This has been corrected so decimal percentage values are now allowed. Also fixed a few grammatical errors on status messages around adding, editing or deleting a risk.
- Risk → Risk Register: If you renamed a WBS or Work Package number via import or the admin, any risks with that old WBS or Work Package code were not being updated. This would cause the user to have to go into each effected risk and reselect the new WBS or Work Package code that was renamed. The system has been updated so that if you rename a WBS or Work Package code, the system now updates the Risk Items WBS / Work Package, too.
- Admin → Import → Risk Items: The Risk Item import template has been enhanced to make it more clear how to successfully upload risks into Dash360. Also, added more error handling messages to alert you when you upload improper data into this area of the application.
- Schedule → Schedule Builder: If you were viewing the Schedule Builder on a system view and then saved an activity, the group by, sort by and columns filters would reset to the default. This has been corrected so that the system will now remember these pre-selected items. However, it is strongly recommended that you always use a user view when changing the schedule. Otherwise, leaving the page and coming back will reset to the default system view.
- Estimating → WBS Dictionary: When downloading the WBS Dictionary into PDF or Word format, the report would show the WBS code twice for each line. This has been corrected.
- Reporting → Staffing Plan Report: User views on this page would sometimes cause the fiscal year columns “FY” to get out of order. The only way to fix the issue was to recreate your user view. This has been corrected so date columns are always in order.
- Earned Value → CPR → Variance Explanations: There was a divide by 0 error showing up for some customers when accessing the variance explanations screen. This has been corrected.
- Wrong Fiscal Year Possible on Earned Resource Assignment Timephased Data: There was a bug that was corrected where the fiscal year on Earned Resource Assignments was sometimes incorrect. The system also now corrects the Fiscal Year column on Earned Resource Assignment’s timephased data if you change your calendar format or when your fiscal year begins in the Admin → Project → Edit Project form.