Skip to main content

Overview

The Earned Value Curves report plots three core EVM metrics over your project timeline as S-curves — Budget (BCWS), Earned Value (BCWP), and Actual Cost (ACWP). The shape and relative position of these curves tells you at a glance whether you are ahead of or behind schedule and whether you are over or under budget. Below the chart, a summary grid shows the key performance metrics for the previous cumulative, current period, and current cumulative positions.

Prerequisites

  • Select a project from the project selector.
  • Select a reporting period from the reporting period selector. The chart and summary grid do not load until both filters are set.

Reading the Chart

The chart plots three spline curves over your project timeline:
CurveEVM TermWhat It Means
BudgetBCWS — Budgeted Cost of Work ScheduledThe planned value of all work scheduled through each period
Earned ValueBCWP — Budgeted Cost of Work PerformedThe planned value of work actually completed through each period
Actual CostACWP — Actual Cost of Work PerformedWhat the completed work actually cost through each period
Reading the gap between curves:
  • If the Earned Value curve is below the Budget curve, the project is behind schedule (negative Schedule Variance).
  • If the Actual Cost curve is above the Earned Value curve, the project is over budget (negative Cost Variance).
Click any legend item to show or hide that curve. Hover over a data point to see the exact value.

Summary Grid

Below the chart, a summary grid shows the following metrics for the previous cumulative, current period, and current cumulative positions:
MetricDefinition
SVSchedule Variance = BCWP − BCWS. Negative = behind schedule.
CVCost Variance = BCWP − ACWP. Negative = over budget.
SPISchedule Performance Index = BCWP ÷ BCWS. Below 1.0 = behind schedule.
CPICost Performance Index = BCWP ÷ ACWP. Below 1.0 = over budget.
BACBudget at Completion — the total approved budget for the project.
EACEstimate at Completion — auto-calculated as ACWP + (BAC − BCWP) ÷ CPI.
VACVariance at Completion = BAC − EAC. Negative means the project is forecast to finish over budget.

Available Filters

FilterWhat It Controls
ProjectThe project to analyze
Reporting PeriodSets the “as of” date for all calculations
AxisToggle between Monthly and Yearly time increments on the chart
WBSLimit the curves to a specific WBS element
Work PackageLimit to a specific work package
CAMLimit to a specific Control Account Manager
Start / End DateZoom the chart to a specific date range
Currency DivisorDisplay values in base dollars, thousands (K), or millions (M)

When to Use This Report

Use EV Curves at the start of any status review to establish the overall performance picture before diving into the CPR detail. The S-curve immediately reveals whether performance is improving or degrading over time — something a tabular report alone cannot show.

Exporting

Click Export to download a multi-sheet Excel workbook. The chart is embedded as an image in the export alongside the summary data grid.

Saved Views

EV Curves supports named saved views that preserve your column layout, filters, and grouping. Your administrator has set up a System View that loads by default. You can save your own named views and switch between them using the view selector in the toolbar. Earned Value Curves